MINUTES
DEPARTMENT OF WATER & POWER
BOARD OF COMMISSIONERS
MINUTES OF A SPECIAL BOARD MEETING
MAY 31, 2007
A Special meeting of the Board of Commissioners of the
Department of Water & Power, City of Big Bear Lake,
was called to order at 9:02 a.m., by Chairwoman Willey,
at the DWP Board Room,
41972 Garstin Drive, Big Bear Lake, California.
FLAG SALUTE:
Board Member Giamarino
BOARD MEMBERS PRESENT:
Barbara Willey, Chairwoman
Susan Conley, Vice Chairwoman
Bill Speyers, Treasurer
Fred Miller, Board Member
Bill Giamarino, Board Member
BOARD MEMBERS EXCUSED:
None
OTHERS PRESENT:
Jerry Gruber, General Manager
Scott Heule, Assistant General Manager
Diane Muir, Administrative Manager
Steve Wilson, Water Superintendent
Robyn Bratton, Board Secretary
J. P. Montero, President, Bear Valley Paving
Two Representatives from WEKA, Inc.
AGM Heule called our City Attorney, Mike Riddell, of Best Best & Krieger
so he would be available to the Board and staff for questions on the proposed
actions regarding awarding of the Lower Moonridge Pipeline Replacement Project.
ITEM NO. 4 - Award Lower Moonridge Pipeline
Replacement Project to the Lowest Responsive
Bidder
AGM Heule reviewed his staff report with the Board and
there was interaction between Board, staff, and Mr. Riddell.
ITEM NO.
3 - Public Forum
J.P. Montero, President of Bear Valley Paving, addressed
the Board regarding his concerns on how the bid was awarded,
referencing the City Ordinance (No. 92-221) that allows
the DWP to award to a local contractor, if the bid is close
to the lowest responsive bidder. Mr. Montero also stated
that on the mandatory pre-bid job walk, the DWP’s
Engineer, Alda Engineering stated that the bid would be
based on a combination of the “main” and “alternate” bids.
AGM Heule stated that the language in Ordinance No 92-221
is permissive, but not mandatory and that it does not obligate
the DWP to give the 1 percent preference to the contractor.
Mr. Riddell stated that if the DWP chose to implement Ordinance
92-221, Mr. Montero still would not be the lowest bidder.
Attorney Mike Riddell also stated that the bid was only
based on the “main” bid and not a combination
of both bids. Mr. Montero did not qualify for the main
bid. The DWP always determines award according to the main
bid unless otherwise stated. There was general discussion
between Mr. Riddell, the Board, and staff.
Becky Himle, from WEKA, Inc. addressed the Board and gave
some background about their company and that they were
eager to begin construction of the pipeline replacement.
ITEM NO. 4 - Award Lower Moonridge Pipeline
Replacement Project to the Lowest Responsive
Bidder
Motion made by Board
Member Giamarino, seconded by Vice Chairwoman, and
carried 5-0 to accept staff’s recommendation
to award the Lower Moonridge Pipeline Replacement
Project to the lowest responsive bidder, WEKA, Inc.,
in the amount of $652,364, and budget internally
for a 10 percent contingency for a total amount of
$717,600. |
ITEM NO. 5 - ADJOURN